Listening Quiz: Kiểm Tra Và Nghiệm Thu Hệ Thống MEP Mới – Medium Level
Th5 12, 2025
—
bởi
Anna Phạm
trong
Tiếng Anh dành cho Kỹ sư xây dựng (English for Civil Engineer)
‹
1
2
3
4
5
›
1.
What is the first test they need to perform on the new MEP system?
Perform a pressure test on the plumbing system
Test airflow and temperature control
Check the electrical connections
Do the final inspection
Explanation:
James says, ‘First, we check the electrical connections.’
2.
How do they test the plumbing system?
By inspecting the electrical connections
By reviewing the commissioning report
By doing a pressure test to find leaks
By checking airflow
Explanation:
James explains that they ‘do a pressure test to find leaks’ for the plumbing system.
3.
When should the final inspection be done?
As soon as the electrical connections are checked
Only after the system is being used
Before any tests are performed
After all tests are complete and passed
Explanation:
James says the final inspection should happen ‘after all tests are complete and passed.’
4.
Who must approve the commissioning report?
Sarah and James
The plumbing and HVAC teams
The electrical inspector and contractor
The project manager and client
Explanation:
James states that ‘The project manager and client must approve it.’
5.
What can be inferred about using the system before approval?
It is considered safe if only one test is finished
It should be avoided because it is unsafe
It can begin once the plumbing test is complete
It is allowed if the final inspection is done
Explanation:
James says they cannot start using the system before approval because ‘it is unsafe without full approval.’
Previous
Check
Next
Finish
Reset
Luyện tập thêm về bài học này:
Listening Lesson
Vocabulary Flashcards and Quiz
←
Trước đó:
Flashcards và Quiz Từ Vựng: Chào mừng một thành viên mới trong đội – Easy Level
Tiếp theo:
Tiếng Anh Quản Lý Chuỗi Cung Ứng: Trình bày báo cáo bền vững chuỗi cung ứng – Medium Level
→